Floor 08

Scan 20

Floors seven and eight

Drag the cloud to orbit

2,184,220 points

Floors seven and eight went up in five weeks, helped by a dry September and a second formwork set that arrived early.

What changed

Moving the rebar yard to the north side cut crane trips by a third. We keep that setup for the remaining floors.

Five weeks for two slabs, with one rain day lost.