Floor 09

Scan 22

Floor nine is poured

Drag the cloud to orbit

2,184,220 points

Concrete for floor nine set over two nights. The pour started at 22:00 on the 12th to keep the slab out of the afternoon heat and finished just after four the next morning.

Where we stand

With nine of fourteen floors standing, the structure is 64% complete. The crane climbs to its final height next week, and the facade team starts the first brick panels on the north side in December.

Next scan

The next scan is due on the 16th of December. Buyers get the cloud link by email the same day.

Floor seven owners can walk their homes from mid January, hard hats provided.

Create a free website with Framer, the website builder loved by startups, designers and agencies.